Kuta Beach Coastal Protection Project Reaches 31 Percent Completion, Sand Filling Still Delayed
Jan. 7, 2026
The Kuta Beach coastal protection and revitalization project has recorded significant progress, reaching 31 percent completion as of early January 2026, far exceeding the initial target of around 10 percent for this stage.